Jahra Road Project mpc
Louis Berger pace

Phase 5 is situated in the middle of the project, where Jahra Road meets Ghazali Road. It consists of the units 21 and 22 of the main line, the Ghazali Bridge and 4 ramps.

Ramps JRK and JRL transfer the traffic from the Ghazali Bridge to the Jahra main line in direction of Kuwait city.

Ramps GRB and GRC are on- and off-ramps to the Ghazali service roads.

Actual work done in phase 5

Bridge piles 63%
Pile Caps 55%
Piers stem 55%
Piers crown 43%
Diaphragms 42%
Segment erection 34%